Want to Remodel in 2027? Start This Winter.

Every spring we get the same call. Someone wants their kitchen done by the Fourth of July, and it's already March.
Sometimes we can make it work. Usually we can't, and it's not because anybody dragged their feet. A remodel done right has months of work that happens before anyone picks up a hammer. If you want to be living in a finished space next year, the clock starts this winter.
Here's what that clock actually looks like.
The part nobody sees
On our projects, the time before construction usually breaks down like this:
Design and selections: 60-120 days. Layout, cabinetry, tile, fixtures, lighting. This is where the project gets good, and it's where rushing costs the most.
Finalization: 30-60 days. Because we design and build under one roof, we price as we go. This step locks the final number. It's not where you find out it's too high. It's where that final 10% of work happens.
Permits: 30-60 days. This depends on where you live. Fort Collins, Loveland, Windsor, Timnath and Larimer County each run on their own timeline.
Ordering: 30 days. Custom cabinets, windows and some appliances take a while to show up. We don't start demo until the long-lead items are on the way, so you aren't living in a gutted kitchen waiting on a box. This timeline can vary the most and we try to run it alongside the finalization and permitting, depending on the client.
Add it up and you're looking at roughly 4 months from our first meeting to demo day. Start in December and you're building in Q2. Start in March and you're building in Q3 along with everyone else who started in March.
Why winter is the best time to plan
Most people don't think about remodeling between Thanksgiving and New Year's. That's exactly why it's a good time to start.
You get our full attention before the spring rush. You get time to make decisions slowly, and slow decisions are cheaper decisions. (We wrote about why in What a Remodel Actually Costs in Northern Colorado.) And you get a free test run of your house.
Use the holidays as a test run
The next seven weeks are the hardest your house will work all year. Pay attention. Keep a note on your phone and write down every time the house gets in your way:
Where do people pile up in the kitchen while you're cooking?
Where do the dirty dishes end up with nowhere to go?
Is there a line for the bathroom?
Where do coats, shoes and bags land when people walk in?
Where does everyone end up sitting, and is there room?
That list is worth more than a Pinterest board. It's the start of a design brief, written by your own house.
What to do before January
Keep the holiday list.
Pick a number you're comfortable with. Our real cost ranges are here.
Save a few photos of spaces you love. Not sure what your style is? Start here.
Have the first conversation before the year ends. It's 30 minutes, and you'll walk away knowing whether your timeline and your budget line up.
Thinking about 2027?
If there's a project you keep putting off, this is the winter to stop putting it off. Grab 30 minutes with us here, and we'll map out what it would take to be done next year.
No pressure, no sales pitch. Just a calendar and some real talk.